Southern Ute Fiber Maintenance 2/5/2025, scheduled 1 week ago

A Fiber Distribution Hub requires relocation to accommodate growth. The maintenance requires us to disconnect the fibers at the FDH and secure them while construction lifts the FDH and digs around the base to move the FDH over about 6 inches in order for the feeder duct to the FDH to be repositioned.

The window will be from 10PM unto 4AM. Based on this move, we believe we will be done within a couple of hours at the most, barring any unforeseen issues.

Affected customers should expect significant downtime during the operational window.

Number of customers affected: 5